The existing 185mm2 4core SWA DNO (emergency) power supply from the street to Oxford Circus station was disconnected and replaced with a 150mm2 4 core SWA supply from a new local DNO transformer (installed by others).


The isolation and changeover required preplanning and notification to all affected end users due to the DNO supply being switched off throughout the whole station.


Upon commissioning of the new supply, the station was checked to ensure all DNO end equipment was fully functional & operational. The work scope included the removal of the redundant feeder cable plus the relocation of Moving Image Advertising power supplies.






Projects


Oxford Circus - DNO Power Supply Changeover

Overview

      Home      About Us      Services       Projects      Contact Us

    Home      Contact      Staff Log In

Solution Rail Limited © 2015

All rights reserved. Terms and Conditions

Chesham


Solution Rail_Projects_Chesham

Ruislip Depot -  Train Refresh


Solution Rail_Projects_Ruislip Train

SSL Pre-Asset Stabilisation Surveys


Solution Rail_Projets_SSL Surveys

Bank DLR


Solution Rail_Projects_Bank

Ruislip Depot -  Road 38


Solution Rail_Projects_Ruislip Road 38

TfL Offices - Electrical Surveys

Solution Rail_Projects_TfL Offices Solution Rail_Projects_Chesham Solution Rail_Projects_Ruislip Train Solution Rail_Projects_Bank Solution Rail_Projets_SSL Surveys Solution Rail_Projects_Ruislip Road 38 Solution Rail_Projects_TfL Offices Solution Rail_Projects_Waterloo Depot Solution Rail_Projects_Oxford Circus

Oxford Circus DNO Power Supply

Solution Rail_Projects_TfL Offices

Waterloo Depot - Train Wash Screen

Solution Rail_Projects_TfL Offices

Go Back


FS 558770